Kerala Chief Minister V. D. Satheesan has said the Adani Group did not attempt to transfer its 49% stake in Adani Vizhinjam Port Private Limited (AVPPL), the company operating Vizhinjam International Port, without the state government’s prior approval. The clarification came in a reply to an unstarred question in the Kerala Legislative Assembly.

Satheesan said AVPPL had submitted an application seeking approval for the proposed transfer of its existing 49% shareholding. Under the concession agreement, any change in the ownership of the concessionaire through a share transfer requires prior approval from the state government.
An empowered committee headed by the Chief Secretary is examining the proposed transaction, the information submitted and other relevant provisions of the concession agreement. The government will take further action based on the committee’s report and recommendations after a comprehensive review.
Adani Group’s Proposed $1.4 Billion Stake Sale
The clarification comes amid the proposed sale of Adani Ports and Special Economic Zone’s (APSEZ) 49% stake in AVPPL to Switzerland-based Mediterranean Shipping Company (MSC), the world’s largest shipping and logistics group.
In June 2026, APSEZ announced that MSC would acquire the stake for approximately $1.4 billion, triggering a political controversy in Kerala. On July 1, Satheesan told the Assembly that the government had learnt about the proposed transaction through media reports and had not received formal communication from APSEZ at that time.
He had also stated that the ownership of the port concessionaire could not be changed without prior government approval.
Vizhinjam Port Expansion Progress
Construction of Vizhinjam International Port began on December 5, 2015, during the Oommen Chandy government. The first phase was completed, and the port began commercial operations on December 3, 2024.
The expansion under Phases II, III and IV is scheduled for completion by December 31, 2028, under the Settlement Agreement signed on February 23, 2024, and the Supplementary Concession Agreement signed on November 28, 2024.
Environmental clearance for the expansion was obtained on March 10, 2025, and construction began in September 2025. Work on extending the breakwater, dredging and reclamation, and constructing the container berth is progressing simultaneously.
According to the Chief Minister’s reply, the expansion works had achieved 12.4% physical progress as of August 2026. The proposed stake transfer remains subject to the state government’s approval following the empowered committee’s review.